Montoir-de-Bretagne LNG terminal breaks European records
Published by Alex Hithersay,
Editorial Assistant
LNG Industry,
Elengy's Montoir-de-Bretagne LNG terminal (France) has reached three separate milestones in August.
The terminal received 13 tankers for four unloadings, three reloadings and three transshipments of LNG cargo within a single month – a record for Europe. The week of 15 August included saw Elengy’s teams complete three LNG transshipments within seven days, a first for a European LNG terminal. In the same week, the terminal completed its tenth LNG transshipment since the beginning of the year, boosting it to first place in Europe in this area.
The results come after a wave of investment to help modernise the facilities at the terminal. Increased collaboration with the operators at the Nantes-Saint-Nazaire port allowed two LNG carriers to moor simultaneously at the Montoir-de-Bretagne terminal’s two berths, in order to safely transfer cargo from one to the other.
Originally designed to unload and regasify LNG brought by ship from countries like Algeria, Nigeria, Norway or Qatar, Montoir-de-Bretagne now offers ship reloading services from its own LNG tanks and direct transshipments of cargo between two vessels. Since 2013, the site has included an LNG tanker truck loading station to supply industrial sites not connected to the grid. To meet growing demand for LNG, Elengy has expanded its daily tanker truck loading capacity by 50% since 2016.
Read the article online at: https://www.lngindustry.com/regasification/31082018/montoir-de-bretagne-lng-terminal-breaks-european-records/
You might also like
IEEFA: Tidal wave of new LNG supply to flood market amid demand uncertainty
Sluggish demand growth for LNG, combined with a record increase in global export capacity through 2028, will likely thrust markets into an extended period of oversupply, according to the latest Global LNG Outlook from the Institute for Energy Economics and Financial Analysis.