Skip to main content

Equinor awards Hammerfest LNG FEED contract to Aibel

Published by , Editor
LNG Industry,


On behalf of the Snøhvit Unit partners, Equinor has awarded Aibel a front-end engineering and design (FEED) contract for the modification of the Hammerfest LNG plant, in connection with the Snøhvit Future project.

The FEED contract has an estimated value of NOK 140 million and will contribute with about 80 man-years for Aibel. All work under the FEED contract will be performed in Norway. The FEED work will cover two sub-projects under the Snøhvit Future development: onshore compression and Hammerfest LNG electrification.

“Snøhvit Future is a complex project that will require large modification work at the Hammerfest LNG plant. By awarding the FEED contract to Aibel we enable continuity and experience transfer. Aibel knows the plant well, having provided maintenance and modification services there since the production start in 2007”, says Peggy Krantz-Underland, Equinor Chief Procurement Officer.

The first sub-project involves the construction of an onshore compression station at the Hammerfest LNG plant. As the pressure in the wells on the Snøhvit field decreases, there will be a need for pressure support to maintain plateau production at the plant. The onshore compression station would be expected to contribute to an increase of the recovery factor from the Snøhvit field. Equinor and partners plan a concept select decision for the compression scope during autumn 2020.

The second sub-project is related to investigating electrification of the Hammerfest LNG plant to minimise the Snøhvit carbon footprint. By replacing current gas turbines with power from shore, it may be possible to reduce CO2 emissions to near zero. Equinor and partners plan a concept select decision for the electrification scope in the end of 2020.

“With the Snøhvit Future project we aim to ensure further value creation from the Snøhvit field and to deliver on our ambitions for emission reductions in Norway. The Snøhvit field contains enough gas to maintain production beyond 2050, and Hammerfest LNG will secure jobs for many years to come,” says Trond Bokn, Acting Senior Vice President for Project Development in Equinor.

Equinor and partners are working towards two final investment decisions (FIDs) for the sub-projects in 2H21.

Given FIDs and regulatory approval Equinor and partners have the possibility to exercise for each sub-project an option for engineering, procurement, construction, and installation (EPCI), that is included in the FEED contract.

The Snøhvit partners together with Aibel will use the next year to plan the work in detail to ensure it can be executed safely and efficiently. During the FEED period Aibel will also have a close dialogue with local suppliers of relevant goods and services about opportunities that may come up during the implementation stage of the sub-projects. Earlier this year Equinor conducted an industry seminar in Hammerfest to inform local suppliers about the project and help them establish a relationship with the potential main contractors.

The Snøhvit Unit partners are: Equinor Energy AS (operator), Petoro AS, Total E&P Norge AS, Neptune Energy Norge AS, and Wintershall Dea Norge AS.

Read the article online at: https://www.lngindustry.com/liquid-natural-gas/04092020/equinor-awards-hammerfest-lng-feed-contract-to-aibel/

You might also like

Silverstream and Yiu Lian Dockyards sign MoU

Silverstream Technologies has signed a memorandum of understanding with Yiu Lian Dockyards (Shekou) Ltd with the aim to drive retrofit installations of the Silverstream® System for vessels dry docking.

 
 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

LNG project news Current LNG projects LNG news in Europe