Golar Power completes reliability test at Sergipe LNG-fuelled power plant

Published by
LNG Industry,


Golar Power Ltd has successfully completed the final operational test at the 1.5GW Sergipe LNG-fuelled power plant.

The test involves supplying the maximum load of the plant (1.5 GW) to the National Interconnected System (SIN) for a period of 96 continuous hours. The test is the final requirement of the National System Operator (ONS) in order to start commercial operations under the 25-year power purchase agreements.

For the test, the three gas turbines, the steam turbine and three heat recovery boilers operated in a combined cycle and delivered a volume in excess of 1.5GW, for 96 continuous hours.

Read the article online at: https://www.lngindustry.com/small-scale-lng/18032020/golar-power-completes-reliability-test-at-sergipe-lng-fuelled-power-plant/

You might also like

 STATS Group

[WEBINAR] Digital Shipbuilding: A Transparent and Real-Time View of the Fabrication Process is Possible

In this webinar, Ismo Piirainen and David Whittle of Hexagon PPM will be discussing the digitalisation and digital transformation trends driving Industry 4.0, especially when it comes to fabrication. Register for free today »

 
 
 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

LNG project news Current LNG projects