Golar Power completes reliability test at Sergipe LNG-fuelled power plant
Published by Will Owen,
Editor
LNG Industry,
Golar Power Ltd has successfully completed the final operational test at the 1.5GW Sergipe LNG-fuelled power plant.
The test involves supplying the maximum load of the plant (1.5 GW) to the National Interconnected System (SIN) for a period of 96 continuous hours. The test is the final requirement of the National System Operator (ONS) in order to start commercial operations under the 25-year power purchase agreements.
For the test, the three gas turbines, the steam turbine and three heat recovery boilers operated in a combined cycle and delivered a volume in excess of 1.5GW, for 96 continuous hours.
Read the article online at: https://www.lngindustry.com/small-scale-lng/18032020/golar-power-completes-reliability-test-at-sergipe-lng-fuelled-power-plant/
You might also like
EIA: US natural gas trade will continue to grow with the start-up of new LNG export projects
The U.S. Energy Information Administration’s recently released Short-Term Energy Outlook forecasts that US LNG exports will continue to lead growth in US natural gas trade as three LNG export projects currently under construction start operations and ramp up to full production by the end of 2025.