Corpus Christi Liquefaction files FERC report forecasting train completions in 2019

Published by
LNG Industry,


Corpus Christi Liquefaction (CCL) has filed a report with FERC projecting that CCL's LNG production Train 1 will achieve substantial completion in March 2019 and Train 2 will achieve substantial completion in September 2019.

The report covers construction activity at CCL's LNG production and export facility at Corpus Christi, Texas, through December 2017.

Read the article online at: https://www.lngindustry.com/liquid-natural-gas/26012018/corpus-christi-liquefaction-files-ferc-report-forecasting-train-completions-in-2019/

You might also like

 CryoTech 2020

CyroTech 2020

Professionals in the LNG sector can tune in from anywhere in the world and learn about the cutting-edge technology and the latest innovations in cryogenics – a fundamental component of the industry.

Register for your free space today »

 
 
 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

LNG project news Cheniere LNG news