Skip to main content

Thiess wins further Wheatstone LNG contract

LNG Industry,


Thiess Pty Ltd has secured a contract with Bechtel to undertake site preparation works for the downstream portion of the Chevron-operated Wheatstone LNG project. The total contract value is estimated at AU$ 450 million.

Thiess will undertake the bulk and final-finish earthworks for the plant, storm water drainage system and access roads around the project.

“Thiess brings to the sector a proven track record in managing the logistical challenges of these large geographically dispersed projects and we look forward to growing our involvement in the bourgeoning LNG industry both in Western Australia and Queensland,” said Thiess Managing Director Bruce Munro.

This is the company’s fourth contract on the Wheatstone LNG project. In joint venture with various international partners, Thiess is already contracted to Bechtel to construct the materials offloading facility and LNG and condensate tanks. Thiess is also contracted to Chevron to deliver the Wheatstone microtunnel.

Work will begin onsite in early fourth quarter 2012 with site preparation works scheduled for completion in early 2014.

Thiess is also completing the construction village and the site preparation and temporary facilities for Chevron on the Gorgon LNG project at Barrow Island.

Adapted from press release by Peter Farrell