Gorgon LNG maintenance planned by Chevron
Published by Will Owen,
Editor
LNG Industry,
According to the latest Reuters report, Chevron Corp. is making plans to carry out maintenance at the Gorgon LNG project. The maintenance rounds will be undertaken in two separate periods this year and in 2020.
More than half an LNG train will reportedly be shutdown from 11 October to 29 November 2019, and more than a full train between 23 May and 11 July 2020.
At full capacity, Gorgon LNG can produce 15.6 million tpy of LNG from its three trains.
The project is operated by Chevron (47.3%), with Exxon Mobil Corp. and Royal Dutch Shell each holding 25% stakes. The remaining 2.7% is held by Osaka Gas, Tokyo Gas and JERA.
Read the article online at: https://www.lngindustry.com/liquid-natural-gas/16102019/gorgon-lng-maintenance-planned-by-chevron/
You might also like
Australia’s ‘golden age of gas’ falls short of hype after decade of LNG exports
The reality of Queensland’s LNG export industry has failed to live up to expectations, plagued by cost blowouts and asset write-downs.