Skip to main content

NextDecade provides 4Q23 business update

Published by , Editor
LNG Industry,


NextDecade Corp. has provided an update on developmental and strategic activities for 4Q23 and early 2024.

“We are committed to maximising long-term value for NextDecade's shareholders by executing our business strategy efficiently and effectively,” said Matt Schatzman, NextDecade's Chairman and CEO. “We are focused on constructing Phase 1 at the Rio Grande LNG Facility safely, on time, and on budget, and delivering a positive FID of our fully permitted expansion capacity to meet growing global demand for cleaner energy sources including LNG.”

“We have a steadfast commitment to upholding the highest standards of safety and excellence in project management and are working alongside our EPC partner, Bechtel, and other counterparties to ensure that construction activities proceed smoothly and in line with contractual schedules. Through rigorous planning, diligent execution, and proactive risk management, together we are seeking to maximize the efficiency of construction efforts.”

“We are also actively working to capitalize on market opportunities and position the company for sustained growth through expansion of our operational footprint. With regulatory approvals in place, our Train 4 and 5 expansion capacity is well-positioned to meet growing global demand for LNG. Supportive market conditions provide tailwinds to continue progressing toward FID of Train 4, which is well underway. Commercial discussions with various potential counterparties and the FEED and EPC contracting processes are proceeding well. Our progress remains aligned with our goal of reaching a positive final investment decision for Train 4 in the second half of this year.”

“Through disciplined execution on Phase 1 and our expansion capacity at the Rio Grande LNG Facility, we are poised to achieve our long-term objective of becoming a leading provider of LNG to customers around the globe while also delivering sustainable growth and value creation for our shareholders.”

Significant recent developments

Development and construction

Under the EPC contracts with Bechtel Energy Inc., Phase 1 progress is tracked for Train 1, Train 2, and the common facilities on a combined basis and Train 3 on a separate basis. As of January 2024:

  • The overall project completion percentage for Trains 1 and 2 and the common facilities of the Rio Grande LNG Facility was 14.3%, which is in line with the schedule under the EPC contract. Within this project completion percentage, engineering was 47.9% complete, procurement was 26.8% complete, and construction was 1% complete.
  • The overall project completion percentage for Train 3 of the Rio Grande LNG Facility was 4.4%, based on preliminary schedules, which is also in line with the schedule under the EPC contract. Within this project completion percentage, engineering was 3.4% complete, procurement was 10.6% complete, and construction was 0% complete.

Strategic and Commercial

The company has started the FEED and EPC contract processes with Bechtel for Train 4 and are progressing numerous discussions with potential buyers of LNG to provide commercial support for Train 4. The EPC contracting process and commercial discussions are progressing at a pace consistent with the company's target of reaching a positive final investment decision (FID) of Train 4 in 2H24.

Financial

As of December 2023, Rio Grande’s outstanding fixed-rate debt and executed interest rate swaps have reduced its exposure to movements in interest rates for approximately 84% of the debt currently projected to be incurred in support of Phase 1 construction.

In December 2023, Rio Grande LNG, LLC entered into a credit agreement with a group of lenders for $251 million of senior secured loans to finance a portion of Phase 1. The senior secured loans were disbursed in one advance of US$251 million on 28 December 2023, which resulted in a reduction in the commitments outstanding under Rio Grande's existing bank credit facilities for Phase 1. These senior secured loans will be amortised over a period of approximately 18 years beginning in mid-2029, with a final maturity in September 2047. These senior secured loans bear interest at a fixed rate of 7.11% and rank pari passu to Rio Grande's existing senior secured financings.

In January 2024, the company's wholly-owned subsidiary NextDecade LNG, LLC entered into a credit agreement that provides for a US$50 million senior secured revolving credit facility with additional capacity of US$12.5 million to cover interest. Borrowings under the revolving credit facility may be used for general corporate purposes, including development costs related to Train 4 at the Rio Grande LNG Facility. Borrowings will bear interest at SOFR or the base rate plus an applicable margin as defined in the credit agreement. The revolving credit facility and interest term loan mature at the earlier of two years from the closing date or 10 business days after a positive FID on Train 4.

In February 2024, Rio Grande issued and sold US$190 million of senior secured notes in a private placement transaction to finance a portion of Phase 1. The senior secured notes were issued on 9 February 2024 and resulted in a reduction in the commitments outstanding under Rio Grande's existing bank credit facilities for Phase 1. These senior secured notes will be amortised over a period of approximately 18 years beginning in mid-2029, with a final maturity in June 2047. The senior secured notes bear interest at a fixed rate of 6.85% and rank pari passu to Rio Grande's existing senior secured financings. Rio Grande has syndicated a portion of its bank credit facility commitments, resulting in a supporting lender group of approximately 40 international banks.

Rio Grande LNG Facility

NextDecade is constructing and developing the Rio Grande LNG Facility on the north shore of the Brownsville Ship Channel in south Texas through its partially-owned subsidiary Rio Grande. The site is located on 984 acres of land which has been leased long-term and includes 15 000 ft of frontage on the Brownsville Ship Channel. The Rio Grande LNG Facility has received necessary approvals and authorisations required for construction, including those from the Federal Energy Regulatory Commission (FERC) and the Department of Energy (DOE), which allow for development, construction, and operation of up to five trains and 27 million tpy of LNG exports.

Phase 1 (Trains 1 – 3)

Phase 1 at the Rio Grande LNG Facility is under construction. Phase 1 includes three liquefaction trains with a total nameplate capacity of 17.61 million tpy of LNG production, two 180 000 m3 full containment LNG storage tanks, and two jetty berthing structures designed to load LNG carriers up to 216 000 m3 in capacity. Phase 1 also includes associated site infrastructure and common facilities including feed gas pretreatment facilities, electric and water utilities, two totally enclosed ground flares for the LNG tanks and marine facilities, two ground flares for the liquefaction trains, roads, levees surrounding the entire site, and warehouses, administrative, operations control room, and maintenance buildings.

As of January 2024, progress on Trains 1 – 3 is in line with the schedule under the EPC Contracts. Recent construction activities have included the start of Train 1 foundation concrete pours, piling activity for the LNG tanks, and construction of the levee and marine offloading facility. Additionally, the civil works program has progressed via the deep soil mixing programme, and meaningful progress has been made on the shoreline restoration program, with the majority of shoreline reclamation nearing completion, and shoreline protection work has commenced. Bechtel has also made meaningful progress on purchase orders for Train 3.

NextDecade holds equity interests in the Phase 1 joint venture that entitle it to receive up to 20.8% of the distributions of available cash during operations.

FID on Train 4 and Train 5

NextDecade is targeting a positive FID and commencement of construction of Train 4 and related infrastructure at the Rio Grande LNG Facility in 2H24, and subsequently Train 5 and related infrastructure. Achieving a positive FID of this fully permitted expansion capacity at the Rio Grande LNG Facility will be subject to, among other things, finalising and entering into EPC contracts, entering into appropriate commercial arrangements, and obtaining adequate financing to construct each train and related infrastructure.

The company has commenced certain pre-FID activities for Train 4, including the FEED and EPC contract processes with Bechtel. The company expects to finalise the Train 4 EPC contract in 1H24.

TotalEnergies SE has LNG purchase options of 1.5 million tpy for each of Train 4 and Train 5. If TotalEnergies exercises its LNG purchase options, the company currently estimates that an additional approximately 3 million tpy of LNG must be contracted on a long-term basis for each of Train 4 and Train 5 prior to making a positive FID for the respective train. The company continues to advance commercial discussions with various potential counterparties and expects to finalise commercial arrangements for Train 4 in the coming months to support an FID of Train 4 in 2H24.

The company expects to finance construction of Train 4 utilising a combination of debt and equity funding. The company expects to enter into bank facilities for the debt portion of the funding. In connection with consummating the Rio Grande Phase 1 equity joint venture, the company's equity partners each have options to invest in Train 4 and Train 5 equity, which, if exercised, would provide approximately 60% of the equity funding required for each of Train 4 and Train 5. Inclusive of these options, NextDecade currently expects to fund 40% of the equity commitments for each of Train 4 and Train 5, and to have an initial economic interest of 40% in each of Train 4 and Train 5, increasing to 60% after its equity partners achieve certain returns on their investments in each of the respective trains. The company expects to undertake the financing process for Train 4 after the EPC contract and commercial arrangements are finalised.

Read the article online at: https://www.lngindustry.com/liquid-natural-gas/12032024/nextdecade-provides-4q23-business-update/

You might also like

 
 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

LNG project news