Hillabee expansion project to begin in May 2016
                            
                                
                                
                                        
                                            
                                        
                                
                                    
                                        Published by David Rowlands,
                                        Editor
                                        
                                    
                                LNG Industry,
                                
                            
                        
Following recent approval from the Federal Energy Regulatory Commission (FERC), Williams Partners has announced that construction on its Hillabee expansion project will commence in May 2016. By May 2021, the expansion will add approximately 1.13 million dekatherms per day of pipeline capacity to the Transco system, which currently delivers gas through a 10 200 mile long pipeline network in the US. Williams Partners expects that the first phase of the three-phase project will enter service in May 2017.
The Senior Vice President of Williams Partners’ Atlantic-Gulf operating area, Rory Miller, said: “We’re excited to move forward as planned with this critical piece of infrastructure to help meet long-term natural gas needs in Florida.
“The Hillabee expansion is among several fully contracted interstate pipeline projects Williams Partners is executing on to connect North America’s abundant natural gas supplies to demand growth from the local distribution, electric power generation, industrial and LNG export businesses.”
The expansion project will involve building approximately 43 miles of new pipe segments in Alabama, as well as a new compressor facility in Choctaw County (Alabama) and changes to existing valve sites and compressor stations.
Edited from press release by David Rowlands
Read the article online at: https://www.lngindustry.com/liquid-natural-gas/11032016/hillabee-expansion-project-to-begin-in-may-2016-2112/
You might also like
Capital Clean Energy Carriers provides fleet employment update
Capital Clean Energy Carriers has secured employment for an LNG carrier currently under construction at Hyundai Samho, which is scheduled for delivery from the shipyard in 1Q27.
 
                                