Sabine Pass Liquefaction Project progressing
Published by Callum O'Reilly,
Senior Editor
LNG Industry,
Sabine Pass has filed a construction progress report to the US Federal Energy Regulatory Commission (FERC) for May 2016.
According to the report, overall project completion of stage 1 at the Sabine Pass Liquefaction Project, located in Cameron Parish, Louisiana, US, is 98.8%, against a planned 99.8%. Engineering and procurement is 100% complete at stage 1, while subcontract and direct hire construction work stood at 93.9% and 98.4%, respectively.
Overall project completion of stage 2 is 86% against the planned 94.2%, while stage 3 completion is ahead of schedule at 35.1% completion compared to a planned 28.6%.
Train 1 substantial completion was achieved on 27 May 2016, and the company expects Train 2 to be completed by late September 2016. The targeted substantial completion dates for Trains 3 and 4 are April 2017 and August 2017, respectively. Scheduled recovery is expected in the summer of 2016 as labour resource is transitioned from stage 1 to stage 2.
Edited from press release by Callum O'Reilly
Read the article online at: https://www.lngindustry.com/liquefaction/23062016/sabine-pass-liquefaction-project-progressing-2650/
You might also like
Viva Energy’s proposed gas terminal receives federal environmental approval
Viva Energy’s proposed gas terminal in Geelong has received formal approval under the Federal Environment Protection and Biodiversity Conservation Act.