Dominion Cove Point LNG files January construction update

Published by , Senior Editor
LNG Industry,


Dominion Cove Point LNG L.P. has filed monthly status and progress report to the US Federal Energy Regulatory Commission (FERC) for January 2016.

In the report, Dominion Cove Point LNG said that construction of its liquefaction project in Lusby, Maryland, US, is 24% complete. Engineering on the project is 97% complete and procurement is 89% complete.

Construction activities throughout the January period included continued mobilisation, site work, foundation work and piping fabrication. However, Dominion Cove Point LNG notes that construction activities were slowed by a major snow storm that occurred during 22 – 24 January 2016.


Edited from press release by

Read the article online at: https://www.lngindustry.com/liquefaction/22022016/dominion-cove-point-lng-files-january-construction-update-2028/

You might also like

Small scale LNG to the rescue

In our recent April issue of LNG Industry, Cathy Farina, General Manager Product Development, PolaireTech International Inc., and Aditya Hegde, General Manager, Polairetech India Private Ltd, explore how small scale LNG is gaining popularity in unlocking and commercialising local stranded gas resources, enabling a sustainable transition to cleaner energy.

 
 

Embed article link: (copy the HTML code below):