Sabine Pass LNG Train 2 commissioning begins
Published by Callum O'Reilly,
Senior Editor
LNG Industry,
The US Federal Energy Regulatory Commission (FERC) has authorised Sabine Pass Liquefaction LLC and Sabine Pass LNG L.P. to introduce feed gas and refrigerants in certain areas related to the commissioning of Train 2 at the Sabine Pass export facility in Cameron Parish, Louisiana, US.
The approval was granted based on FERC staff inspections and review of filed information on 6 April and 15 April 2016.
The approval does not authorise the introduction of natural gas or process fluids into the areas not identified in the Sabine Pass request.
Edited from press release by Callum O'Reilly
Read the article online at: https://www.lngindustry.com/liquefaction/20042016/sabine-pass-lng-train-2-commissioning-begins-2315/
You might also like
Commonwealth LNG signs 20-year SPA with Asian buyer
Commonwealth LNG has signed a sale and purchase agreement with a major Asian energy company for 1 million tpy of LNG for 20 years from Commonwealth’s facility currently under development in Louisiana.