Video: installation of subsea structures for Shell’s Prelude FLNG vessel
Published by David Rowlands,
Editor
LNG Industry,
Shell has released a video showing the undersea installation of the anchor piles, christmas trees and manifolds for the Prelude floating LNG (FLNG) vessel. The video can be viewed below.
The installation was completed in 21 days, which was eight days ahead of schedule. There were no incidents during the operation.
Edited from various sources by David Rowlands
Read the article online at: https://www.lngindustry.com/liquefaction/13042016/video-installation-of-subsea-structures-for-shells-prelude-flng-vessel-2278/
You might also like
Shell invests in Nigeria offshore gas development
Shell Nigeria Exploration and Production Co. Ltd and Sunlink Energies and Resources Ltd have taken a final investment decision on the HI gas project offshore Nigeria.