Video: installation of subsea structures for Shell’s Prelude FLNG vessel
Published by David Rowlands,
Editor
LNG Industry,
Shell has released a video showing the undersea installation of the anchor piles, christmas trees and manifolds for the Prelude floating LNG (FLNG) vessel. The video can be viewed below.
The installation was completed in 21 days, which was eight days ahead of schedule. There were no incidents during the operation.
Edited from various sources by David Rowlands
Read the article online at: https://www.lngindustry.com/liquefaction/13042016/video-installation-of-subsea-structures-for-shells-prelude-flng-vessel-2278/
You might also like
IEEFA: Tidal wave of new LNG supply to flood market amid demand uncertainty
Sluggish demand growth for LNG, combined with a record increase in global export capacity through 2028, will likely thrust markets into an extended period of oversupply, according to the latest Global LNG Outlook from the Institute for Energy Economics and Financial Analysis.