FERC approves Gulf South Pipeline’s pre-filing request
The US Federal Energy Regulatory Commission (FERC) has approved Gulf South Pipeline’s request to commence the pre-filing environmental review of its proposed Coastal Bend Header Project.
The project consists of the construction of approximately 65 miles of 36-in. diameter pipeline, interconnecting Tennessee Gas Pipeline Company’s system in Wharton County, Texas, with the Freeport LNG terminal in Brazoria County, Texas.
The project will provided approximately 1.54 billion ft3/d of gas to serve the Freeport LNG liquefaction terminal, and will include two new compressor stations, as well as modifications at two existing compressor stations.
Gulf South intends to file an application no later than 12 June 2015.
Edited from various sources by Katie Woodward
Read the article online at: https://www.lngindustry.com/liquefaction/07112014/gulf-south-pipeline-to-commence-pre-filing-review-1747/
You might also like
EIA: US natural gas trade will continue to grow with the start-up of new LNG export projects
The U.S. Energy Information Administration’s recently released Short-Term Energy Outlook forecasts that US LNG exports will continue to lead growth in US natural gas trade as three LNG export projects currently under construction start operations and ramp up to full production by the end of 2025.