Corpus Christi Liquefaction construction update

Published by , Senior Editor
LNG Industry,


Corpus Christi Liquefaction LLC has issued its monthly construction progress report for November 2015, regarding the Corpus Christi Liquefaction Project.

According to the report, engineering at the Corpus Christi Liquefaction Project has progressed to 92.1% complete, while procurement stood at 39.6%. Bechtel’s construction has progressed to 1.4%. The total liquefaction project is now 27.7% complete.