Polskie LNG receives 84th cargo delivery at Swinoujscie terminal
Published by David Rowlands,
Editor
LNG Industry,
According to the post, this is the sixth delivery alone in 2020, with further cargoes scheduled for delivery this month.
The LNG terminal has an annual regasification capacity of 5 billion Nm3, and includes two 160 000 m3 LNG storage tanks. Polskie LNG is currently implementing an expansion plan, which consists of the following four elements:
- Further regasification installation: increasing the nominal regasification capacity of the terminal to 7.5 billion Nm3/yr.
- Third LNG process storage tank: increasing the operational flexibility of the LNG terminal installation and ensuring the optimum natural gas process storage capacity.
- LNG-to-rail transhipment installation: increasing the list of services provided with the possibility of natural gas transhipment onto ISO containers and rail tankers and thereby reaching new potential customers.
- Second jetty: for loading and unloading of LNG carriers, LNG transhipment and handling LNG bunker vessels and providing bunkering services.
Read the article online at: https://www.lngindustry.com/regasification/19022020/polskie-lng-receives-84th-cargo-delivery-at-winoujcie-terminal/