Cove Point Liquefaction status update
Published by Callum O'Reilly,
Senior Editor
LNG Industry,
Dominion Cove Point LNG LP has submitted its updated status report to the Federal Energy Regulatory Commission (FERC) regarding the construction and operation of the Cove Point Liquefaction Project.
For the October 2015 review period, engineering is now 97% complete. Procurement is 81% complete and construction is 18% complete.
The work scope completed at the terminal included form, reinforce, and placement for the following equipment foundations: the main cryogenic heat exchanger (MCHE), LNG pumps, mixed refrigerant (MR) separator, nitrogen stripper, amine tanks, sub-station columns, thermal oxidizer, and north gas turbine building. All sound wall columns have also been installed with the exception of the posts at the entrance of the terminal.
Edited from various sources by Callum O'Reilly
Read the article online at: https://www.lngindustry.com/liquid-natural-gas/23112015/cove-point-liquefaction-status-update-1660/
You might also like
Delfin Midstream enters agreement with Siemens Energy to reserve gas turbine manufacturing capacity
Delfin Midstream Inc. has entered into an agreement with Siemens Energy Inc. to reserve manufacturing capacity for four SGT-750 gas turbine mechanical drive packages and an early works programme with Samsung Heavy Industries and Black & Veatch to further floating LNG vessel design specifications.