Dominion Cove Point LNG files January construction update
Published by Callum O'Reilly,
Senior Editor
LNG Industry,
Dominion Cove Point LNG L.P. has filed monthly status and progress report to the US Federal Energy Regulatory Commission (FERC) for January 2016.
In the report, Dominion Cove Point LNG said that construction of its liquefaction project in Lusby, Maryland, US, is 24% complete. Engineering on the project is 97% complete and procurement is 89% complete.
Construction activities throughout the January period included continued mobilisation, site work, foundation work and piping fabrication. However, Dominion Cove Point LNG notes that construction activities were slowed by a major snow storm that occurred during 22 – 24 January 2016.
Edited from press release by Callum O'Reilly
Read the article online at: https://www.lngindustry.com/liquid-natural-gas/22022016/dominion-cove-point-lng-files-january-construction-update-2028/
You might also like
Capital Group invests in Kongsberg simulators for new training centre
Kongsberg Maritime has secured a contract with Capital Group to deliver advanced K-Sim Engine Room and Cargo simulators for their training centre on the Greek island of Chios.