Golar Power completes reliability test at Sergipe LNG-fuelled power plant
Published by Will Owen,
Editor
LNG Industry,
Golar Power Ltd has successfully completed the final operational test at the 1.5GW Sergipe LNG-fuelled power plant.
The test involves supplying the maximum load of the plant (1.5 GW) to the National Interconnected System (SIN) for a period of 96 continuous hours. The test is the final requirement of the National System Operator (ONS) in order to start commercial operations under the 25-year power purchase agreements.
For the test, the three gas turbines, the steam turbine and three heat recovery boilers operated in a combined cycle and delivered a volume in excess of 1.5GW, for 96 continuous hours.
Read the article online at: https://www.lngindustry.com/liquid-natural-gas/18032020/golar-power-completes-reliability-test-at-sergipe-lng-fuelled-power-plant/
You might also like
Saipem awarded offshore EPCI contract by QatarEnergy LNG
Saipem, in partnership with Offshore Oil Engineering Co. Ltd, has been awarded an offshore EPCI contract by QatarEnergy LNG for the COMP5 package of the North Field Production Sustainability Offshore Compression Complexes project.