Video: installation of subsea structures for Shell’s Prelude FLNG vessel
Published by David Rowlands,
Editor
LNG Industry,
Shell has released a video showing the undersea installation of the anchor piles, christmas trees and manifolds for the Prelude floating LNG (FLNG) vessel. The video can be viewed below.
The installation was completed in 21 days, which was eight days ahead of schedule. There were no incidents during the operation.
Edited from various sources by David Rowlands