Yamal LNG reaches full capacity
Published by David Rowlands,
Editor
LNG Industry,
According to the statement, this milestone has been reached a year ahead of the initial schedule and within the original budget. The Yamal facility has now reached its full planned capacity of 16.5 million tpy less than one year after the first shipment of LNG from the project in December last year.
Total claims that the startup of Train 3 has occurred one week after the project shipped its 100th LNG cargo.
The Chairman and CEO of Total, Patrick Pouyanné, said: “We are proud of the successful launch of all three LNG trains of the Yamal LNG project less than a year after the startup of the plant. This constitutes an unprecedented achievement for the industry.
“The positive experience of Yamal LNG paves the way for further LNG developments alongside our strategic partner Novatek, including Arctic LNG 2, the next major development based on giant low costs resources in Russia’s far north.”
Read the article online at: https://www.lngindustry.com/liquid-natural-gas/11122018/yamal-lng-reaches-full-capacity/
You might also like
Axpo and GNV complete first ship-to-ship bio-LNG refuelling in Italy
Axpo and GNV supported by the Maritime Authority of Genoa, have completed Italy's first ship-to-ship bio-LNG bunkering operation at the Port of Genoa.