Corpus Christi project update
Published by Callum O'Reilly,
Senior Editor
LNG Industry,
Corpus Christi Liquefaction LLC has submitted its monthly construction progress report for the Corpus Christi Liquefaction Project.
According to the September 2015 report, the total project has progressed to 22.8% complete against a planned 17.8%. Engineering has progressed to 82%, procurement has progressed to 32% and Bechtel’s construction has progressed to 0.4%.
The LNG project reported no environmental, safety and health incidents during the month.
Planned activities for October 2015 are also said to be on track.
Edited from press release by Callum O'Reilly
Read the article online at: https://www.lngindustry.com/liquid-natural-gas/03112015/corpus-christi-project-update-september-2015-1565/
You might also like
Dragon LNG partners with Worley to explore integration of LNG and CO2 liquefaction processes
Dragon LNG has awarded a contract to Worley to conduct a comprehensive feasibility study focusing on exploring the potential benefits of integrating LNG regasification and carbon dioxide liquefaction processes at Dragon LNG’s facilities.