Corpus Christi Liquefaction provides progress update
Published by Callum O'Reilly,
Senior Editor
LNG Industry,
Corpus Christi Liquefaction LLC has submitted its monthly construction progress report to the Federal Energy Regulatory Commission (FERC) for July 2015.
The reports states that the Corpus Christi Liquefaction Project has progressed to 18.9% complete against a planned 14.1%. The total LNG engineering has progressed to 71.9% and procurement has progressed to 25.9%. The subcontract and direct hire construction are 0% and 0.1%.
The report also states that there were no reported environmental, safety and health related events throughout the month, and that activities planned for August 2015 are on track.
Edited from press release by Callum O'Reilly
Read the article online at: https://www.lngindustry.com/liquefaction/27082015/corpus-christi-liquefaction-provides-progress-update-1207/
You might also like
Golar agrees 20-year re-deployment charter for FLNGs
Golar LNG Ltd has announced the final investment decision and fulfilment of all conditions precedent for the 20-year re-deployment charter of the FLNG Hilli Episeyo.