Corpus Christi Liquefaction provides progress update

Published by , Senior Editor
LNG Industry,


Corpus Christi Liquefaction LLC has submitted its monthly construction progress report to the Federal Energy Regulatory Commission (FERC) for July 2015.

The reports states that the Corpus Christi Liquefaction Project has progressed to 18.9% complete against a planned 14.1%. The total LNG engineering has progressed to 71.9% and procurement has progressed to 25.9%. The subcontract and direct hire construction are 0% and 0.1%.

The report also states that there were no reported environmental, safety and health related events throughout the month, and that activities planned for August 2015 are on track.


Edited from press release by

Read the article online at: https://www.lngindustry.com/liquefaction/27082015/corpus-christi-liquefaction-provides-progress-update-1207/

You might also like

Eni and YPF move closer to Argentina LNG FID

Eni and YPF have signed a final technical project description, an important step toward reaching the final investment decision for a 12 million tpy LNG phase of the integrated upstream-midstream Argentina LNG project.

 
 

Embed article link: (copy the HTML code below):