Corpus Christi Liquefaction June 2016 construction report
Published by Callum O'Reilly,
Senior Editor
LNG Industry,
Corpus Christi Liquefaction LLC has issued its monthly construction report to the US Federal Energy Regulatory Commission (FERC) for June 2016.
According to the report, engineering on the project has progressed to 98.4%. At the end of June, procurement stood at 50.6%, while Bechtel’s direct hire construction was 8.8%.
The total LNG project has progressed to 36.6% complete, while activities planned for the month of July 2016 are on track.
Edited from press release by Callum O'Reilly
Read the article online at: https://www.lngindustry.com/liquefaction/26072016/corpus-christi-liquefaction-june-2016-construction-report-2818/
You might also like
Excelerate Energy signs definitive agreement for Iraq FLNG import terminal
Excelerate Energy, Inc. has executed a definitive commercial agreement with a subsidiary of Iraq’s Ministry of Electricity for the development of the country’s first LNG import terminal at the Port of Khor Al Zubair.