Sabine Pass November 2015 construction update
Published by Callum O'Reilly,
Senior Editor
LNG Industry,
Sabine Pass LNG L.P. and Sabine Pass Liquefaction LLC (Sabine Pass) has submitted its monthly construction progress report for November 2015, regarding the Sabine Pass Liquefaction Project.
According the to report, stage 1 and stage 2 engineering and procurement are 100% complete, while engineering for stage 3 is 33.5% complete and procurement is 18% complete.
Subcontract work stood at 85.9%, 51.2% and 11.6% complete for stages 1 – 3, respectively. Stage 1 direct hire work is 95.2% complete, while stage 2 direct hire work is 51.5% complete.
Overall project completion is behind schedule, with stage 1 at 96.9% against the plan of 98.7%, stage 2 at 78.2% against the plan of 83.3% and stage 3 at 12.6% against the plan of 12.7%.
Edited from press release by Callum O'Reilly
Read the article online at: https://www.lngindustry.com/liquefaction/04012016/sabine-pass-november-2015-construction-update-1825/
You might also like
Stabilis Solutions announces extension of LNG fuel contract
Stabilis Solutions, Inc. has announced the extension of its LNG supply agreement with a leading global provider of on-demand industrial power solutions.