New Fortress to acquire Brazil LNG-to-power project
Published by Will Owen,
Editor
LNG Industry,
US LNG company New Fortress Energy reached an agreement with Brazilian firm Bolognesi Energia to acquire its planned LNG terminal and associated 1.3GW Rio Grande thermoelectric project.
The Rio Grande power plant will use regasified LNG delivered into a FSRU. The complex is worth an estimated US$946 million.
The project won long-term power purchase agreements (PPAs) in a November 2014 auction for supply starting in January 2019, but it is significantly behind schedule. Bolognesi successfully renegotiated the PPAs with distributors and pushed back the start date of the contracts to January 2021.
Although Aneel granted Bolognesi's request for an extension, the regulator gave the company a hard deadline of the end of August to demonstrate the project's viability and to prove it has secured financing and LNG supply. The company also needs to secure environmental permits by 31 December 2017.
New Fortress said it would be working together with Bolognesi to obtain the necessary environmental permits, but did not disclose the size of the transaction. The deal is subject to regulatory approval.
In June, Brazilian firm Prumo Logistica reached an agreement with Bolognesi to buy its Novo Tempo LNG-to-power project.
Prumo said it will seek authorisation to transfer the project location from Pernambuco state to the Port of Acu in Rio de Janeiro state where it plans to develop an LNG gas hub.
New Fortress recently partnered with Jamaica Public Service (JPS) to deliver LNG to Jamaica.
Read the article online at: https://www.lngindustry.com/floating-lng/28092017/new-fortress-to-acquire-brazil-lng-to-power-project/
You might also like
IEEFA: EU combined gas and LNG imports fall due to reduced demand
EU measures to reduce gas demand have driven a decline in the bloc’s combined imports of pipeline gas and LNG, according to a new data tracking tool published by the Institute for Energy Economics and Financial Analysis.