Corpus Christi Liquefaction files May 2016 progress update
Published by Callum O'Reilly,
Senior Editor
LNG Industry,
Corpus Christi Liquefaction LLC has filed its monthly construction report for April 2016 to the US Federal Energy Regulatory Commission (FERC).
According to the report, engineering has progressed to 98%, procurement is now at 46.9% and Bechtel’s direct hire construction through April was 5.7%. As such, the total project has progressed to 33.5% complete.
During the month, engineering focused on continuing to update design for concrete for IAC, lighting plans, grounding plans and cable tray plans. Construction focused on progressing permanent plant concrete and steel, underground pipe, and above ground pipe.
Corpus Christi Liquefaction reported no lost time incidents during the month. The company also confirmed that planned activities for May 2016 are on track.
Edited from press release by Callum O'Reilly
Read the article online at: https://www.lngindustry.com/liquefaction/26052016/corpus-christi-liquefaction-files-may-2016-progress-update-2503/
You might also like
100th LNG carrier arrives at Wilhelmshaven LNG terminal
The 100th LNG carrier arrived at the Wilhelmshaven LNG terminal 01 at Voslapper Groden.