GasLog confirms order of FSRU LLIs

Published by , Senior Editor
LNG Industry,


GasLog Ltd has announced that Keppel Shipyard Ltd has started ordering long lead items (LLIs) required for the conversion of a GasLog or GasLog Partners LP LNG carrier to a floating storage and regasification unit (FSRU).

The LLIs, which take approximately 12 months to deliver at a total cost of around US$16 million, include pumps, vaporisers, heat exchangers and low duty compressors.

Ordering the LLIs reduces the time necessary to convert an LNG carrier from between 18 - 20 months to 6 - 8 months once the LLIs are delivered.

GasLog believes that securing the LLIs at this time will put the company in a position to offer a fast track solution for FSRU projects in the future. GasLog is working on a number of potential projects where the LLIs could be used in a vessel conversion and has a number of well suited candidates for conversion in its fleet of LNG carriers.

Paul Wogan, Chief Executive Officer (CEO) of GasLog Ltd, said: "GasLog's success in developing both its FSRU capability and its industry relationships has allowed the early ordering of the LLIs. This is a reflection of the progress we are making with a number of different projects around the world."

Read the article online at: https://www.lngindustry.com/lng-shipping/05122016/gaslog-confirms-order-of-fsru-llis/

You might also like

 
 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

LNG carrier news