Cove Point Liquefaction status update
Published by Callum O'Reilly,
Senior Editor
LNG Industry,
Dominion Cove Point LNG LP has submitted its updated status report to the Federal Energy Regulatory Commission (FERC) regarding the construction and operation of the Cove Point Liquefaction Project.
For the October 2015 review period, engineering is now 97% complete. Procurement is 81% complete and construction is 18% complete.
The work scope completed at the terminal included form, reinforce, and placement for the following equipment foundations: the main cryogenic heat exchanger (MCHE), LNG pumps, mixed refrigerant (MR) separator, nitrogen stripper, amine tanks, sub-station columns, thermal oxidizer, and north gas turbine building. All sound wall columns have also been installed with the exception of the posts at the entrance of the terminal.
Edited from various sources by Callum O'Reilly
Read the article online at: https://www.lngindustry.com/liquefaction/23112015/cove-point-liquefaction-status-update-1660/
You might also like
Golar agrees 20-year re-deployment charter for FLNGs
Golar LNG Ltd has announced the final investment decision and fulfilment of all conditions precedent for the 20-year re-deployment charter of the FLNG Hilli Episeyo.