TotalEnergies has announced the commissioning of the Cape Ann, its FSRU for LNG located in the port of Le Havre. The terminal injected its first megawatt-hours of gas into the grid operated by GRTgaz, using LNG from Norway.
TotalEnergies has contracted 50% of the terminal's annual capacity of around 5 billion m3, to supply it with LNG from its global portfolio. The remaining capacity will be marketed according to rules approved by the regulator.
Cape Ann key figures:
- Maximum regasification capacity: 5 billion m3/y, or around 10% of French con-sumption.
- Storage capacity: 142 500 m3.
- Vessel dimensions: 283 m x 43.4 m.
- Draught: 12.5 m.
- Deadweight: 112 457 t.
- Lightship: 31 676 t.
- Date of first launch: June 2010.
- Owner: Höegh LNG.
- Flag: French.