The project is located in the vicinity of Sabine Pass, Texas, US.
According to FERC, Golden Pass LNG cited delays in obtaining the necessary authorisations, both from the commission as well as from the Department of Energy’s Office of Fossil Energy (DOE/FE), and the resulting uncertainty as reasons for needing an extension.
In response to this request, FERC stated: “Therefore, Applicants are hereby granted an extension of time until and including November 30, 2026 to complete the construction of the project and make it available for service.”