Tellurian receives FERC scheduling notice for Driftwood LNG

 

Published by
LNG Industry,

Tellurian Inc. has announced that the Federal Energy Regulatory Commission (FERC) has issued the notice of schedule for environmental review of Driftwood LNG and Driftwood Pipeline.

According to the notice, FERC will issue its final Environmental Impact Statement (EIS) on 12 October 2018, and has established a 90-day Federal Authorisation Decision Deadline on 10 January 2019.

Assuming a favourable decision, Tellurian expects that this schedule will allow it to begin construction of Driftwood LNG in early 2019, pending a final investment decision by Tellurian.

 