In March 2016, the US Federal Energy Regulatory Commission (FERC) denied authorisation for the construction and operation of the Jordan Cove LNG terminal and Pacific Connector Gas Pipeline.

Now, Veresen Inc. has released a statement claiming it has received a notice from the US Federal Energy Regulatory Commission (FERC) that it has issued an order granting rehearing for further consideration. This is in response to the company’s request for a rehearing, which was originally submitted on 8 April 2016 by Jordan Cove Energy Project L.P. and Pacific Connector Gas Pipeline L.P.

The order has the limited purpose of noting that a rehearing request has been submitted, and allowing itself more time than the 30-day statutory period to consider the merits of such requests for a rehearing. The request for a rehearing will either be granted or denied by FERC in a later order.

Edited from various sources by David Rowlands

 

Veresen requests rehearing for Jordon Cove and Pacific Connector

The Jordan Cove Energy Project and the Pacific Connector Gas Pipeline have submitted a request to FERC for a rehearing of the commission’s order on 11 March 2016 denying authorisation to construct and operate the Jordan Cove LNG terminal and Pacific Connector Gas Pipeline.

Veresen considers appeal

Veresen has commented on the court decision regarding the Jordan Cove LNG project.