Australia Pacific LNG is 88% complete

 

LNG Industry,

Origin Energy Limited has reported that the Australia Pacific LNG project is 88% complete and on track to deliver first LNG in mid-2015.

APLNG

David Baldwin, the company’s CEO, commented: “We continue to make significant progress in the delivery of the Australia Pacific LNG project.

“The upstream component of the project is 90% complete, with 1019 development wells drilled and 666 wells commissioned, while the downstream component is 86% complete and the final Train 2 module has been set on its permanent foundations.

“The Australia Pacific LNG project remains on track for first LNG in mid-2015.”

Production

Origin reported production for 4Q14 of 33.4 petajoules equivalent (PJe) and sales revenue of $235.6 million.

Production was down 4% on the previous quarter, mainly due to lower production at Otway as a result of maintenance activities and lower customer nominations by Origin, a planned maintenance shutdown at BassGas, as well as lower seasonal demand at Kupe, partly offset by higher production at Australia Pacific LNG.

Sales

Sales revenue decreased 6% compared to the previous quarter, reflecting lower production and a lower average commodity price.


Adapted from press release by Katie Woodward

 

APLNG completes LNG tank testing

Australia Pacific LNG has completed the hydro and pneumatic testing on its second LNG storage tank.

Australia Pacific LNG 75% complete

Origin announces progress of Australia Pacific LNG project and second quarter rises in reserves and production.