Corpus Christi Liquefaction LLC has issued its monthly construction report to the US Federal Energy Regulatory Commission (FERC) for June 2016.
According to the report, engineering on the project has progressed to 98.4%. At the end of June, procurement stood at 50.6%, while Bechtel’s direct hire construction was 8.8%.
The total LNG project has progressed to 36.6% complete, while activities planned for the month of July 2016 are on track.