Sabine Pass project behind schedule

 

Published by
LNG Industry,

Sabine Pass LNG L.P. and Sabine Pass Liquefaction LLC (Sabine Pass) have provided its monthly construction progress report for the Sabine Pass Liquefaction Project.

According to the October 2015 report, the project is slightly behind schedule. Stage 1 (trains 1 and 2) overall project completion is 96.1% compared to the planned 98.2%. Stage 1 engineering and procurement is 100% complete, while subcontract and direct hire construction work are 84.1% and 93.5% complete, respectively.

Overall project completion for stage 2 (trains 3 and 4) is 76.7% against the plan of 81.8%. Engineering at this stage is also 100% complete, with subcontract and direct hire construction work at 50.4% and 48.5%, respectively.

The stage 3 baseline schedule is being finalised and progress reporting will start in November 2015.


Edited from press release by

 

Sabine Pass LNG granted Stage 2 authority

FERC grants Sabine Pass LNG authority to install installation equipment, process and utility systems, and process vessels for Stage 2 at Cameron Parish.

Sabine Pass LNG to become export terminal

The US Department of Energy has issued a conditional authorisation approving an application to export 803 billion ft3/ yr of LNG from the Sabine Pass LNG Terminal in Louisiana.