Skip to main content

Cove Point Liquefaction status update

 

Published by
LNG Industry,

Dominion Cove Point LNG LP has submitted its updated status report to the Federal Energy Regulatory Commission (FERC) regarding the construction and operation of the Cove Point Liquefaction Project.

For the October 2015 review period, engineering is now 97% complete. Procurement is 81% complete and construction is 18% complete.

The work scope completed at the terminal included form, reinforce, and placement for the following equipment foundations: the main cryogenic heat exchanger (MCHE), LNG pumps, mixed refrigerant (MR) separator, nitrogen stripper, amine tanks, sub-station columns, thermal oxidizer, and north gas turbine building. All sound wall columns have also been installed with the exception of the posts at the entrance of the terminal.

Edited from various sources by