Corpus Christi Liquefaction LLC has submitted its monthly construction report for March 2016 to the US Federal Energy Regulatory Commission (FERC).
According to the report, engineering has progressed to 97.1% at the Corpus Christi Liquefaction Project. Procurement now stands at 46%, while Bechtel’s direct hire construction has progressed to 4.6%. The total liquefaction project is now 32.5% complete.
Corpus Christi Liquefaction also confirmed that activities planned for April 2016 are on track.