Corpus Christi Liquefaction LLC has released its latest monthly construction report for the Corpus Christi Liquefaction Project.

According to the report, which covers activities at the LNG project during October 2015, engineering has progressed to 90.3% and procurement now stands at 34.6%. Bechtel’s construction has progressed to 0.8% and the total project is now 25% complete, compared to a planned 19.3% at this stage.

Corpus Christi Liquefaction also confirmed that there were no reported environmental, safety and health related events throughout October 2015.


Edited from press release by

 

Corpus Christi project update

The Corpus Christi Liquefaction project is now 22.8% complete, according the September 2015 progress report.