Skip to main content

Update: Magnolia LNG FERC progress

 

Published by
LNG Industry,

Liquefied Natural Gas Ltd has submitted a further response to the US Federal Energy Regulatory Commission's (FERC) Engineering Data request covering additional geotechnical-seismic items. The response is in relation to the LNG Ltd’s wholly owned subsidiary, Magnolia LNG LLC.

According to LNG Ltd Managing Director and CEO, Maurice Brand, the Magnolia LNG team and consultants had been advised that a further two requests will be made shortly. Mr Brand said: "The FERC process continues to run in parallel with the company moving towards a bankable EPC contract and long-term Tolling Agreements. Magnolia LNG is well placed to achieve its primary goal to achieve Financial Close in mid-2015 and first LNG in 2018."


Adapted from press release by

 

Magnolia LNG and KBR sign TSA

Magnolia LNG has signed a Technical Services Agreement with Kellogg Brown & Root LLC, a wholly owned subsidiary of KBR Inc.

Update: Magnolia LNG

LNG Ltd has confirmed that Magnolia LNG and Kinder Morgan Louisiana Pipeline have submitted responses to two separate environmental information requests from FERC.

Magnolia LNG FERC progress

Liquefied Natural Gas Ltd provided an update on the progress of its FERC application for its Magnolia LNG project.