LNG Ltd provides update
Published by Callum O'Reilly,
Senior Editor
LNG Industry,
Liquefied Natural Gas Ltd (LNG Ltd) has provided an update on the Federal Environmental Regulatory Commission’s (FERC) Environmental Requests relating to its wholly owned subsidiary, Magnolia LNG LLC.
Environmental
On 23 October, Magnolia LNG and Kinder Morgan Louisiana Pipeline (KMLP) received follow-up data requests from FERC covering additional questions on the environmental aspects of the projects. These additional questions are normal and Magnolia LNG will respond directly to the Information Requests it receives from FERC.
Seismic and geotechnical
Magnolia LNG recently submitted responses to FERC's second Information Request covering seismic and geotechnical information.
Technical and safety
LNG Ltd expects to receive an Information Request on the technical and safety Resource Reports submitted. Responses to this Information Request from FERC and any other clarifications required, need to be addressed in order for FERC to issue a Notice of Schedule for Environmental Review followed by the Draft Environmental Impact Statement.
Magnolia LNG is moving substantially closer to the issuance of both documents and is targeting their release in this calendar year.
Adapted from press release by Callum O'Reilly
Read the article online at: https://www.lngindustry.com/liquefaction/27102014/lng-ltd-provides-update-1664/
You might also like
CB&I awarded contract by TotalEnergies and OQ for full containment LNG tank
CB&I has been awarded a contract by Marsa Liquefied Natural Gas LLC, a joint venture between TotalEnergies and OQ, for the EPC of a full containment concrete LNG storage tank, located in Oman's Port of Sohar.