Dominion Cove Point issues May update
Published by Callum O'Reilly,
Senior Editor
LNG Industry,
Dominion Cove Point LNG LP has issued its monthly status and progress report to the US Federal Energy Regulatory Commission (FERC) for May 2016.
According to the report, engineering at the Maryland facilities is now 99.8% complete, engineered equipment procurement is 99% complete andconstruction is 38% complete.
There was a barge equipment delivery during the month. The high pressure knock out drum, and north and south cold flare knock out drums were transported through OAB.
At the terminal, work continued on modifications to the existing plant in the areas of the jetty platforms and tie-in scope. Work scope also continued on foundations, grading, steel erection, equipment placement, piping, tie-in’s, and electrical installation.
Construction activities conducted during May at the Virginia facilities included continued materials delivery, site work, foundation work, piping work, equipment work, and building erection. Work during the May reporting period coincided with an outage of the compressor station and M&R station operations to facilitate construction and tie-in activities.
Edited from press release by Callum O'Reilly
Read the article online at: https://www.lngindustry.com/liquefaction/27062016/dominion-cove-point-issues-may-progress-update/
You might also like
EIA: US natural gas trade will continue to grow with the start-up of new LNG export projects
The U.S. Energy Information Administration’s recently released Short-Term Energy Outlook forecasts that US LNG exports will continue to lead growth in US natural gas trade as three LNG export projects currently under construction start operations and ramp up to full production by the end of 2025.