Corpus Christi Liquefaction March update

Published by , Senior Editor
LNG Industry,


Corpus Christi Liquefaction LLC has submitted its monthly construction report for March 2016 to the US Federal Energy Regulatory Commission (FERC).

According to the report, engineering has progressed to 97.1% at the Corpus Christi Liquefaction Project. Procurement now stands at 46%, while Bechtel’s direct hire construction has progressed to 4.6%. The total liquefaction project is now 32.5% complete.

Corpus Christi Liquefaction also confirmed that activities planned for April 2016 are on track.